The City Council added review in May 2026, before any data center applied.
What did the Hoover City Council change?
In May 2026, the council approved a zoning ordinance change to guard against possible negative impacts from future data centers.
The Hoover Sun reported that Hoover had no data center applications at that time.
How were data centers treated before?
Hoover's ordinance has no classification that specifically defines most modern data centers. The closest is an office/technical use, according to City Planner Mac Martin.
That use was permitted by right in most non-residential districts, and no public hearings would have been required.
What is required now?
Office/technical uses now need conditional use approval.
Any data center application must go to the Hoover Planning Commission and the City Council.
Martin said this lets staff review the concept and advise applicants on the studies they need to submit.
Why did the council act?
Councilman Robin Schultz called it a proactive step so a data center does not appear without proper vetting.
A Ross Bridge resident asked why the council did not set a moratorium instead, as Birmingham did after an application from Nebius.
Read the full month in our November 2026 local update.
See also how a Hoover conditional use vote works.
Sources
Hoover Sun, May 14, 2026, by Jon Anderson: Hoover City Council changes approval process for data centers.